Moyle Interconnector (Financing) plc7Strategic report for the year ended 31 March 2023 (continued)
Strategic objective: Operate assets safely and cost effectively, outsourcing where appropriateOperational performance
As planned, Moyle’s availability was significantly impacted by the Control System Upgrade Project (CSUP) and therefore was 79.9% in 2022/23 (KPI 1). This was significantly reduced compared to 98.9% availability in the previous 12 months, but the vast majority of this reduction related to planned outages.
This major project saw the control and protection system completely replaced, and outages were taken throughout the summer months to allow site works. The two poles were refurbished sequentially, with only short bi-pole outages taken (an initial one day, and subsequent seven days mid-project). This allowed Moyle to continue to offer 250MW capacity for the majority of the period of the site works. Two minor trips occurred after the restoration of the first pole, quickly identified as snagging items with the project. Reliability thereafter was exceptional, with no further trips throughout the remainder of the year. Aside from the CSUP, availability remained excellent; only one trip (with a duration of less than one hour) occurred, and this was due to failure within equipment that was planned to be replaced as part of the CSUP, emphasising the need to undertake the project.
There were no lost time incidents in the year (KPI 2).
Moyle has also been very reliable through the period in delivering DS31 ancillary services to the NI system operator and ‘Balancing and Ancillary Services’ to the GB system operator. These services represent an increased source of revenue, and their reliability is an equally important measure as (capacity) availability. In 2022/23, as in the previous year, these services were provided in full compliance with the contract. These reliability figures are impacted by overall interconnector availability (KPI 1) but also the speed of response of the service when called upon, which in turn is reliant on the technology type of Moyle’s convertors. The CSUP included amendments to the functionality of the convertors to improve the reliability by improving speed of response across a wider range of operational parameters. This has improved Moyle’s system service offering.
A possible emerging trend through 2022/23 is that whilst the ancillary service supporting the NI grid was ‘armed’ by the NI System Operator and available for the entire year, the number of times it activated was significantly less than the previous year.
The GB Operator only ‘armed’ the ancillary service for a couple of very short periods. Nonetheless, CSUP amendments have us better equipped to offer what the system operators might require by way of ancillary service going forward.
Asset Management
The CSUP has been a major focus for Moyle since 2018, the control and protection hardware was obsolete, with support becoming ever more challenging. Reliability was also at risk, as failure modes began to emerge within the aging equipment.
The refurbishment project, which was delivered on time and within budget (project and outage costs), provided enhanced redundancy (and hence reliability), more resilience against fast-changing transmission networks, and more sophisticated ancillary services. Further information on the project is included in the CSUP feature on page 8.
Aside from CSUP, work is ongoing to ensure that reliability is maintained across all Moyle’s sub-components. During the year, new chillers were installed; these maintain constant temperature in the control rooms, providing the ideal environment for electronic equipment to operate reliably. The new chillers also bring a significant energy saving.
1 DS3 Delivering a Secure, Sustainable System - the SONI/EirGrid programme to enable high penetration of renewables on the electricity transmission system.